As promised here is an update from our club president - Mark Nelson:
Court construction is on schedule. The contractor will have the 12 eastern most courts done this week. He will then start on the other 12. If you look at the courts right now they are all green. He puts down the green first. Next he will line out the courts and then go back and fill in the blue playing surface. The playing surface will be U. S. Open Blue. The kitchen and out of bounds will be dark green. Here's a link to a website that shows the colors
Rest Rooms: There
has been a lot of discussion on what we will use for toilets at the new courts.
Palm Creek is bringing in portable toilets that will be hooked to water and
sewer. they will be flush toilets and have running water for washing your hands.
The permanent toilets and snack stand will be built later this
year.