Court Construction Update

Court Construction Time Line

We’re all curious about how the new courts are progressing. Palm Creek provided us with a time line for the sports complex construction. Here’s a brief synopsis of the construction plans for the new courts.

Earth movement and walls to be done between now and August 5th. On August 6th work should start on setting up the cables for the post tension concrete on the 12 eastern courts. Pouring concrete on these courts will start on August 13th.

The 12 western courts will have the post tension work start on August 20th and the concrete is planned to be poured starting August 27th.

After the concrete is poured it will need to cure for 35 days before any work can be done on it. The painting and striping of the courts is planned to start on October 8th and take 2 weeks.

 
Mark Nelson
Club President

Note:  Any additional information will be posted when received